3.4.2020 - UPDATE on 2020 Replacement Projects

PROJECT UPDATE from Utility Director, Josh Becker

Main Street Sewer Line and Sandstone AC Line Replacement Project

The construction on Sandstone is moving along.  There have been a few rain delays, but the rain is always welcome.  The crews will continue to move up Sandstone this month and should be starting on Main Street next month.

The schedule for installing the new water line is as follows:

March 4th thru March 6th - East Sandstone from Walnut to Ash
March 9th thru March 20th - East Sandstone from Ash to Oak
March 23rd thru March 27th - East Sandstone from Oak to Elm, then turning north on Elm Street to Main, then turning west on Main
March 30th thru April 3rd - East Main from Elm to Bailey
April 6th thru April 10th - East Main from Bailey to Oatman
April 13th thru April 17th - Turning north on Oatman to Haynie 

This schedule can change due to weather or other unexpected delays. Please watch the City website for updates along with the back side of your next utilities bill.

During this construction, plan to see detours on East Sandstone. The contractor will work with property owners while work is being done on their block to allow access to and from homes.  Please avoid parking vehicles in the street on East Sandstone from 7 a.m. to 6 p.m. while work is scheduled on your block.

Feel free to call the City of Llano at 325-247-4158 with any questions.